PMP Exam 2017

Free pmp exam simulator free to pass pmp free questions. For pmp exam questions 2017 you must go through real exam. For that we provide pmp exam papers 2017 real test. We discuss in these mock pmp exam from different topics like rita pmp exam prep, pmp mock exam online free 2017.

pmp exam test questions

In this test you have to answer pmp online exam simulator. To get pass sample pmp test you must answers correct. So Enjoy these pmp new exam to get enough knowledge for pmp online questions attempt. You will get mock test answers after click submit button at bottom. If any question wrong just click on go back button to correct it. Easy Na!

2017 pmp exam questions free pmp exam questions 2017 free pmp questions and answers pdf pmp 2017 exam questions pmp 2017 questions pmp certification questions and answers pdf pmp certification sample questions pdf pmp exam 2017 questions pmp exam dumps 2017 pmp exam dumps free download pmp exam papers pdf pmp exam pdf pmp exam prep questions answers & explanations pdf pmp exam questions 2017 pdf pmp exam questions 5th edition pdf pmp exam questions and answers pdf pmp exam questions free download pdf pmp exam questions pdf pmp exam sample questions 2017 pmp exam sample questions pdf pmp mock exam 2017 pmp mock exam pdf pmp mock test 2017 pmp practice exam 2017 pmp practice questions 2017 pmp question bank pdf pmp question bank with answers pdf pmp questions 2017 pmp questions and answers 2017 pmp questions and answers pdf pmp questions pdf pmp real exam questions 2017 pmp risk management questions and answers pdf pmp sample questions and answers pmp sample questions pdf free download pmp test questions pdf project management exam questions and answers pdf project management exam questions answers download project management test questions and answers real pmp exam questions 2017

PMP Practice Exam 7th Edition

pmp practice exam questions pmp certification questions and answers 2017

Print Friendly and PDF


Q:1-Which of the following is tru about the Project Management Plan?
Mark one answer:

Project Management Plan identifies and authorizes the Project Manager.
Project Management Plan is a detailed project schedule defining tasks, their dependencies as well as primary milestones of the project.
Project Management Plan is a formal document that defines how the project is to be managed.
Project Management Plan is prepared as part of the Direct and Manage Project Work process.



Q:2-George is the Project Manager of a project responsible for manufacturing shirts for a large order. During which process the shirts will get manufactured?
Mark one answer:

Develop Project Management Plan
Direct and Manage Project Work
Monitor and Control Project Work
Create WBS


Q:3-Perform Integrated Change Control process is part of which process group?
Mark one answer:

Initiating.
Planning.
Executing.
Monitoring and Control.


Q:4-Greg is a Project Manager of a construction project. The customer has requested that an additional room needs to be constructed at an extra cost? How should Greg respond to this request
Mark one answer:

Document the request and present it to Change Control Board.
Refuse the request as this was not part of the original scope.
Accept the request as the customer is willing to pay for it.
Consult the project sponsor.


Q:5-Michael is the Project Manager of a software project being developed for a large customer. A senior management executive of Michaels organization suggests Michael that adding a new feature will be a good addition to his project. What is the best course of action for Michael?
Mark one answer:

Document the request and present it to change control board.
Refuse the request as this was not part of the original scope.
Accept the request as it is being suggested by a senior member of the organization.
Consult the project sponsor.



Q:6-Doug is a Project Manager for a project to build a bridge. During his review of the progress, Doug finds out that the project is likely to be completed in six months before schedule. Which is the most suitable thing for Doug to do next?
Mark one answer:

Organize a party for the project team to ensure employee motivation remains high.
Raise a change request to reduce staff.
Doug does not need to do anything.
Doug needs to use the additional six months to make sure the bridge exceeds thq quality goals.


Q:7-Which of these is not done during the Close Project process?
Mark one answer:

Creation of deliverables of the project.
The handing over of deliverables to the receiving party.
Documenting the project learnings.
Release of project resources.


Q:8-Mary is taking over an ongoiung project as a Project Manager. The earlier project manager is no more with the organization. Mary wants to understand why the project should be executed, the high level project requirements and budget of the project. Which document should Mary refer to?
Mark one answer:

Project Management Plan.
Project Statement of work.
Business case.
Project charter.


Q:9-The stakeholder analysis matrix is part of ...?
Mark one answer:

Part of the Stakeholder Management Strategy - an output of identify stakeholders
An output of Plan Communications
Part of the stakeholder register
Part of Performance Reporting


Q:10-Which relationship model is most commonly used in the Precedence diagrams?
Mark one answer:

start-to-start
start-to-finish
finish-to-start
finish-to-finish



best pmp practice exams pmp mock exam 6th edition